Tuesday, March 30, 2010

Slab Poured

Hi All

After a few days delay, the slab was poured today.Its all getting very excited now when we can see how the floor plan will look like.The slab was to be poured on 25/03 but was delayed due to some administrative error.
The preslab work was completed on Friday 26/03.The slab could not be poured yesterday because of heavy rain in the morning.
Here are some pics taken on Friday 26/03.
This is close view of the slab.

This is as we look from the back left of the house

Here are some pics of the slab taken today.



























The next stage is the Frame stage where in the Frame will be erected.We will keep you posted with the progress.

Saturday, March 20, 2010

Site Work Started

Finally, work started with site scrap don on 15/03.Went on site yesterday.A portable loo and a bin is already onsite but no temporary fencing yet.May be the fence will be put after the slab is poured which is on 25/03. Electricity has been connected and all the drainage pipes has been laid.











































Wednesday, March 10, 2010

Ready for building

Hi All

At last after a long wait,ready to start building our dream home.Got the letter from the builder yesterday with all the details.Got the building permit also.

Drainage pipes going in the next week and slab has been booked for 25th March.

Here is the photo of the vacant block.











If you wish to see the plan of the house we are building,please visit http://www.carlislehomes.com.au/affinityRange/bordeaux.html